MDA

Ministry of Works

Project Location/State

Enugu State

Award Year

2013

Contract Sum

₦850.5m

Amount Paid

₦127.5m

Unaccounted

₦66.8m

Context/Observation

Contract No. 6221 was awarded with commencement date of 4th December, 2013 and an extended completion date of 3rd December, 2015 at the sum of N850.5m. The amount certified and paid to date was N127.5m. The physical accomplishment was 7.15% valued at N60.8m, with a percentage time lapse of 95.83%. It was observed that the contractor was not on site despite a warning letter issued on 25th February, 2016 by the Controller of Works. Apart from site clearance, little earth works, stone base of just 1.12km and prime coat of 1.09km done by the contractor, there was nothing on ground to justify the payment of N127.5m made to the contractor.

Contractor

N/A

Beneficial Ownership Information

N/A

Legislative Recommendation

N/A

Executive Action

N/A

Progress Report

N/A

Data Source

2016 Audit Report of the Federation

Project Gallery

Click to enlarge image

Seach for project by title, MDA, state, status, year…

Trending projects

Report project
in your community today

Do you know of project(s) in your community that has been abandoned, not executed or poorly implemented. Our team is ready to help you track it and get government to act.

Value for Money allows you to track, report and act on audited development projects abandoned, not executed or poorly implemented in your community to ensure public funds are efficiently, effectively, and economically utilized to improve service delivery to you and other citizens in Nigeria

Contact

Newsletter

Stay in the loop, get all project updates straight in your inbox. 

© 2024 Value for Money. All right reserved.