MDA

Niger Delta Development Commission (NDDC)

Project Location/State

Bayelsa State

Award Year

2013

Contract Sum

₦200m

Amount Paid

₦110.1m

Unaccounted

₦110.1m

Context/Observation

It is recommended as follows:-
• Management should explain why a vigil road construction is put as emergency rehabilitation to circumvent tendering procedures.
• The advertisement, the tenders and other due process that led to the award of the contract should be forwarded to the Office of the Auditor-General for the Federation.
• The Director of Project Monitoring Department should explain why certificate of completion is issued for work that was not completed to mislead the Commission.
• The total sum of N110,127,553.56 that was paid for work not done should be recovered from the contractor in the first instant otherwise the amount should be recovered from those engineers including the Director (PMS) who misled government for the payment.

Contractor

N/A

Beneficial Ownership Information

N/A

Legislative Recommendation

N/A

Executive Action

N/A

Progress Report

N/A

Data Source

AuGF Report on NDDC (2008-2012)

Project Gallery

Click to enlarge image

Seach for project by title, MDA, state, status, year…

Trending projects

Report project
in your community today

Do you know of project(s) in your community that has been abandoned, not executed or poorly implemented. Our team is ready to help you track it and get government to act.

Value for Money allows you to track, report and act on audited development projects abandoned, not executed or poorly implemented in your community to ensure public funds are efficiently, effectively, and economically utilized to improve service delivery to you and other citizens in Nigeria

Contact

Newsletter

Stay in the loop, get all project updates straight in your inbox. 

© 2024 Value for Money. All right reserved.