MDA

Niger Delta Development Commission (NDDC)

Project Location/State

Imo State

Award Year

2012

Contract Sum

₦151.8m

Amount Paid

₦122.5m

Unaccounted

₦44m

Context/Observation

It is recommended by the Auditor General for the Federation that:
(i) The total sum of N31,687,000.00 paid for work not done/executed should be recovered from the contractor in the first instance or failing which the Engineers /officers that sign the valuation certificate, IPCs and practical completion certificate should be made to repay.
(ii) The sum of N12,260,000.00 provide for in item 2.07 and 2.11 of the BEME that was observed to be a duplication of item 2.02 and 2.09 as stated in observation F should also be recovered from the Engineers that prepared and signed the valuation certificate & IPC together with the Executive Director Projects and Director PMS.
Evidence of the recovery should be forwarded to the Office of the Auditor General for the Federation for verification.

Contractor

N/A

Beneficial Ownership Information

N/A

Legislative Recommendation

N/A

Executive Action

N/A

Progress Report

N/A

Data Source

AuGF Report on NDDC (2008-2012)

Project Gallery

Click to enlarge image

Seach for project by title, MDA, state, status, year…

Trending projects

Report project
in your community today

Do you know of project(s) in your community that has been abandoned, not executed or poorly implemented. Our team is ready to help you track it and get government to act.

Value for Money allows you to track, report and act on audited development projects abandoned, not executed or poorly implemented in your community to ensure public funds are efficiently, effectively, and economically utilized to improve service delivery to you and other citizens in Nigeria

Contact

Newsletter

Stay in the loop, get all project updates straight in your inbox. 

© 2024 Value for Money. All right reserved.