MDA

Hadejia Jama’are River Basin Development Authority

Project Location/State

Kano State State

Award Year

2012

Contract Sum

₦48.5m

Amount Paid

₦74m

Unaccounted

₦22.2m

Context/Observation

1. During the physical verification however, the project status indicated a 35% job completion, while a 65% payment has been effected contrary to extant regulations on milestone achievements on project execution vis-a-vis payments.

rnrn

2. Also, the project site was abandoned and the following observations were equally made which require the Managing Director’s comments:
rn(i) Laying of pipes did not start at the treatment plant.
rn(ii) Laying of pipes started from Wudil town to Basaman Fulani.
rn(iii) There were existing old pipes laid from Basaman Fulani to Indabo.
rn(iv) The contractor did not lay new pipes from Basaman Fulani to Indabo.
rn(v) Pipes were not laid at all in the following places – Dagumawa, Tundun Gunsau and Lamire.
rn(vi) Work executed is 35% as indicated in the project status report.

Contractor

N/A

Beneficial Ownership Information

N/A

Legislative Recommendation

N/A

Executive Action

N/A

Progress Report

N/A

Data Source

2014 Audit report of F.G

Project Gallery

Click to enlarge image

Seach for project by title, MDA, state, status, year…

Trending projects

Report project
in your community today

Do you know of project(s) in your community that has been abandoned, not executed or poorly implemented. Our team is ready to help you track it and get government to act.

Value for Money allows you to track, report and act on audited development projects abandoned, not executed or poorly implemented in your community to ensure public funds are efficiently, effectively, and economically utilized to improve service delivery to you and other citizens in Nigeria

Contact

Newsletter

Stay in the loop, get all project updates straight in your inbox. 

© 2024 Value for Money. All right reserved.