MDA

Ogun-Osun River Basin Development Authority (OORBDA), Abeokuta

Project Location/State

N/A State

Award Year

Contract Sum

₦404.8m

Amount Paid

₦561.1m

Unaccounted

₦111m

Context/Observation

Contract was awarded in 2008 for N565.1million, N404.7million was paid, whereas the value of the work done is N293.8million. The contractor was overpaid the sum of N110.9million.

Legislative Recommendation

N/A

Executive Action

N/A

Progress Report

N/A

Data Source

2016 Audit report of F.G

Project Gallery

Click to enlarge image