Ogun-Osun River Basin Development Authority (OORBDA), Abeokuta

Project Location/State

Oyo State

Award Year

2011

Contract Sum

₦307.6m

Amount Paid

₦617.8m

Unaccounted

₦257.6m

Context/Observation

Contract was awarded for N617.8m in May 2011 vide letter referenced FMWR/PD/S/181SUB/7/C/134/VOL.1/1 with 12 months completion period. Although contractor received N307.6m, Inspection to the site revealed that the money paid outweighs actual work done on the project.

Legislative Recommendation

N/A

Executive Action

N/A

Progress Report

N/A

Data Source

2016 Audit Report of the Federation