MDA

Niger Delta Development Commission (NDDC)

Project Location/State

Cross River State

Award Year

2012

Contract Sum

₦150m

Amount Paid

₦135m

Unaccounted

₦30.5m

Context/Observation

It is recommended by the Auditor-General for the Federation that:
i. The outstanding retention of N6,865,005.00 due to this contractor should no longer be paid to him.

ii. The sum of N30,537,219.75 being the difference between the sum of N44,217,600.00 paid for work not done and the outstanding retention of N6,865,005.00 and unpaid items of N6,815,375.25 should be recovered from the contractor, failing which the amount should be recovered from the ED/Projects and the Director PMS together with all the other officers that signed the work valuation documents and interim payment certificates for this contractor to be paid.

Evidence of the recovery should be communicated to the office of the Auditor General for the Federation for verification.

Contractor

N/A

Beneficial Ownership Information

N/A

Legislative Recommendation

N/A

Executive Action

N/A

Progress Report

N/A

Data Source

AuGF Report on NDDC (2008-2012)

Project Gallery

Click to enlarge image

Seach for project by title, MDA, state, status, year…

Trending projects

Report project
in your community today

Do you know of project(s) in your community that has been abandoned, not executed or poorly implemented. Our team is ready to help you track it and get government to act.

Value for Money allows you to track, report and act on audited development projects abandoned, not executed or poorly implemented in your community to ensure public funds are efficiently, effectively, and economically utilized to improve service delivery to you and other citizens in Nigeria

Contact

Newsletter

Stay in the loop, get all project updates straight in your inbox. 

© 2024 Value for Money. All right reserved.