MDA

Nigeria Port Authority (NPA)

Project Location/State

Cross River State

Award Year

2013

Contract Sum

₦836.9m

Amount Paid

₦113.5m

Unaccounted

₦63.8m

Context/Observation

Contract was awarded to a construction company at the cost of N836.9m with 8 months completion period from 5th December, 2013 to 4th August, 2014. An advance payment of N113.5m was made to the contractor. However, only 5.95% of the contract valued at N49.8m was executed. The project which was originally a constituency project for construction of bridge was replaced with the 10.0km Doka Gulu road without due process. Kano State Government constructed a culvert on the location instead of the bridge.

Legislative Recommendation

N/A

Executive Action

N/A

Progress Report

N/A

Data Source

2016 Audit Report of the Federation

Project Gallery

Click to enlarge image

Seach for project by title, MDA, state, status, year…

Trending projects

Report project
in your community today

Do you know of project(s) in your community that has been abandoned, not executed or poorly implemented. Our team is ready to help you track it and get government to act.