MDA

code of conduct Tribunal

Project Location/State

Award Year

2019

Contract Sum

₦₦0.00

Amount Paid

₦₦434,500,000.00

Unaccounted

₦₦434,500,000.00

Context/Observation

Audit observed that:
i. The sum of 434,500,000.00 (Four hundred and thirty four million, five hundred thousand naira) was paid to contractors for projects in Calabar, Kaduna, Bauchi and Enugu.
ii. There was no documentary evidence on the progress of work like Bill of Engineering Measurement and Evaluation (BEME), Consultants Interim Payment Certificate (IPC) and payment vouchers in respect of the payments, and
iii. The level of work done for which payments were made could not be ascertained due to refusal of the Tribunal to lead the auditors on inspection of project sites.

Contractor

N/A

Beneficial Ownership Information

N/A

Legislative Recommendation

The Chief Registrar is requested to:
i. Furnish reasons why payments for capital projects were made without supporting documents as required by extant regulations.
ii. Provide the Original Payment Vouchers with relevant documents like Letter of Award of Contracts, Bill of Engineering Measurement and Evaluation (BEME), Consultants Interim Payment Certificate (IPC) in respect of work done in Calabar, Kaduna, Bauchi and Enugu;
iii. Recover the sum of 434,500,000.00 (Four hundred and thirty four million, five hundred thousand naira) from the contractors and remit same to the Treasury.
iv. Forward evidence of remittance to the Public Accounts Committees of the National Assembly, and
v. Otherwise, apply sanctions relating to irregular payment and gross misconduct specified in paragraphs 3106 and 3129 of the Financial Regulations respectively.

Executive Action

N/A

Progress Report

N/A

Data Source

2019 Non compliance Audit report of the FG

Project Gallery

Click to enlarge image

No submitted petition history found

Want to submit petition to Anti-Corruption Agency on this issue?

Let our “VfM AI” tool help you generate a unique petition and send it instantly to your preferred Anti-Corruption Agency for investigation!

Use "Submit Petition" button below to proceed

Seach for project by title, MDA, state, status, year…

Trending projects

Report project
in your community today

Do you know of project(s) in your community that has been abandoned, not executed or poorly implemented. Our team is ready to help you track it and get government to act.

Value for Money allows you to track, report and act on audited development projects abandoned, not executed or poorly implemented in your community to ensure public funds are efficiently, effectively, and economically utilized to improve service delivery to you and other citizens in Nigeria

Contact

Newsletter

Stay in the loop, get all project updates straight in your inbox. 

© 2025 Value for Money. All right reserved.