Federal Medical Centre, Keffi

Project Location/State

Award Year

2019

Contract Sum

₦₦0.00

Amount Paid

₦₦76,529,361.22

Unaccounted

₦₦76,529,361.22

Context/Observation

I.The first firm is a consultant that deployed EMR Software called Careplus while second firm is a consultant/agent that collects revenue and remit to the Centre’s account.
II.The contract file of the first firm was not made available to audit.
III.The Centre provided a contract file of the second firm but without relevant procurement documents to show that due process was followed as there was no evidence of solicitation documents like company’s tax clearance certificate, three years audited account, evidence of advertisement in at least two (2) national dailies and Federal Tenders Board.
IV.The Centre did not maintain Procurement Committee and Parastatal’s Tenders Board meeting documents hence non of the minutes of the meetings were made available to the audit.
V.The Centre paid the sum of N76,529,361.22 to both the first and second firm, broken down as N26,433,750.00 and N29,650,000.00 in 2017 and 2016 respectively for the first firm and N20,445,561.43 for the second firm representing N655,860.00, N5,091,653.43, N7,133,204.69, and N7,564,892.21 for 2016, 2017, 2018 and 2019 respectively, and
VI.The Centre could not generate sales report to enable audit ascertain the completeness of the revenue collected by the agent.

Contractor

N/A

Beneficial Ownership Information

N/A

Legislative Recommendation

The Chief Medical Director is requested to:
I.Furnish reasons for violating the procurement due process
II.Provide the minutes of the Tenders Board meetings which were supposed to be kept for a minimum of 10 years otherwise,
III.Recover the sum of N76,529,361.22 and pay back to chest
IV.Forward the evidence of remittance to the Public Accounts Committees of the National Assembly.
V.Otherwise, apply sanctions relating to offences and sanctions under the Public Procurement Act (PPA) and paragraph 3125 of the Financial Regulations.

Executive Action

N/A

Progress Report

N/A

Data Source

2019 Non-Compliance Audit Report of the FG

Project Gallery

Click to enlarge image

No submitted petition history found

Want to submit petition to Anti-Corruption Agency on this issue?

Let our “VfM AI” tool help you generate a unique petition and send it instantly to your preferred Anti-Corruption Agency for investigation!

Use "Submit Petition" button below to proceed

Seach for project by title, MDA, state, status, year…

Trending projects

Report project
in your community today

Do you know of project(s) in your community that has been abandoned, not executed or poorly implemented. Our team is ready to help you track it and get government to act.

Value for Money allows you to track, report and act on audited development projects abandoned, not executed or poorly implemented in your community to ensure public funds are efficiently, effectively, and economically utilized to improve service delivery to you and other citizens in Nigeria

Contact

Newsletter

Stay in the loop, get all project updates straight in your inbox. 

© 2025 Value for Money. All right reserved.