MDA

Niger Delta Development Commission (NDDC)

Project Location/State

Abia State

Award Year

2015

Contract Sum

₦485,128,179.79

Amount Paid

₦153,834,462.20

Unaccounted

₦153,834,462.20

Context/Observation

The Management should justify why the consultancy reports for the studies and design were received and approved long after the main contracts were awarded and even executed. The Management should be held liable for negligence and refund the sum of ₦153,834,462.20. Evidence of refund forwarded to the Office of the Auditor-General for the Federation for verification.

Contractor

MESSRS. VC CONSULTING SERVICES LTD

Beneficial Ownership Information

N/A

Legislative Recommendation

N/A

Executive Action

N/A

Progress Report

N/A

Data Source

AuGF Report on NDDC (2013-2018)

Project Gallery

Click to enlarge image

Seach for project by title, MDA, state, status, year…

Trending projects

Report project
in your community today

Do you know of project(s) in your community that has been abandoned, not executed or poorly implemented. Our team is ready to help you track it and get government to act.

Value for Money allows you to track, report and act on audited development projects abandoned, not executed or poorly implemented in your community to ensure public funds are efficiently, effectively, and economically utilized to improve service delivery to you and other citizens in Nigeria

Contact

Newsletter

Stay in the loop, get all project updates straight in your inbox. 

© 2024 Value for Money. All right reserved.