MDA

Ogun-Osun River Basin Development Authority (OORBDA), Abeokuta

Project Location/State

N/A State

Award Year

2010

Contract Sum

₦221m

Amount Paid

₦221m

Unaccounted

₦44.3m

Context/Observation

Contract was awarded for N221million in October 2010 through award letter Referenced OOR/BDA/S/349/2010/Vol.I/004 with 6 (six) months completion period. Although the contractor was paid N221m, N44.3million was spent without evidence and work done was partially executed.

Legislative Recommendation

N/A

Executive Action

N/A

Progress Report

N/A

Data Source

2016 Audit report of F.G

Project Gallery

Click to enlarge image