MDA

Ogun-Osun River Basin Development Authority (OORBDA), Abeokuta

Project Location/State

Oyo State

Award Year

2010

Contract Sum

₦318.9m

Amount Paid

₦365.7m

Unaccounted

₦218.9m

Context/Observation

Phase 1 was awarded in August 2010 for N154.5m with 18 (eighteen) months completion period while Phase 2 was awarded to the same contractor in August 2013 vide award letter referenced OORBDA/S/462/1/23A/S/454/2013/Vol.1/007 for N221.3m with 12 months completion period. However, Phase two was minutely done.

Contractor

N/A

Beneficial Ownership Information

N/A

Legislative Recommendation

N/A

Executive Action

N/A

Progress Report

N/A

Data Source

2016 Audit Report of the Federation

Project Gallery

Click to enlarge image

Want to submit petition to Anti-Corruption Agency on this issue?

Let our “VfM AI” tool help you generate a unique petition and send it instantly to your preferred Anti-Corruption Agency for investigation!

Use "Submit Petition" button below to proceed

Seach for project by title, MDA, state, status, year…

Trending projects

Report project
in your community today

Do you know of project(s) in your community that has been abandoned, not executed or poorly implemented. Our team is ready to help you track it and get government to act.

Value for Money allows you to track, report and act on audited development projects abandoned, not executed or poorly implemented in your community to ensure public funds are efficiently, effectively, and economically utilized to improve service delivery to you and other citizens in Nigeria

Contact

Newsletter

Stay in the loop, get all project updates straight in your inbox. 

© 2024 Value for Money. All right reserved.