MDA

University Of Port Harcourt Teaching Hospital (UPTH)

Project Location/State

Rivers State State

Award Year

2011

Contract Sum

₦113.3m

Amount Paid

₦244.3m

Unaccounted

₦22m

Context/Observation

1. N91,307,268.95 was first paid and another N22,000,000.00 was equally paid to the contractor in 2013.

rnrn

2. Physical site inspection carried out on the project on the 5th of November, 2013 indicated that the contractor had vacated the project site for more than a year, long before this last payment of N22,000,000.00 was made and this was evident by the bushy surrounding at the project site, dilapidated and decayed wooden form work and scaffolding.

rnrn

3. Contained in the IPC No. 5 issued on the 6th of December, 2012 was the sum of N3,500,000.00 for the value of material on site. Since the contractor has vacated site for over a year, these materials ought to be physically present at the project site as at the time of audit inspection but contrarily not so. Therefore, the claim for N3,500,000.00 as value of material on site could not be justified.

Contractor

N/A

Beneficial Ownership Information

N/A

Legislative Recommendation

N/A

Executive Action

N/A

Progress Report

N/A

Data Source

2014 Audit report of F.G

Project Gallery

Click to enlarge image

Seach for project by title, MDA, state, status, year…

Trending projects

Report project
in your community today

Do you know of project(s) in your community that has been abandoned, not executed or poorly implemented. Our team is ready to help you track it and get government to act.

Value for Money allows you to track, report and act on audited development projects abandoned, not executed or poorly implemented in your community to ensure public funds are efficiently, effectively, and economically utilized to improve service delivery to you and other citizens in Nigeria

Contact

Newsletter

Stay in the loop, get all project updates straight in your inbox. 

© 2024 Value for Money. All right reserved.