MDA

Federal University Birnin-Kebbi, Kebbi State

Project Location/State

Kebbi State

Award Year

2017

Contract Sum

₦127.7m

Amount Paid

₦67m

Unaccounted

₦67m

Context/Observation

Contract for the construction of a Library Block at the College of Health Sciences was awarded in the contract sum of ₦127,733,520.67, on 17th March, 2015, with a completion period of 24 weeks. During the periodic check in November 2017, we observed that the sum of ₦67,028,049.25, representing 52% of the contract sum had been paid to the contractor. Even though the project was supposed to have been handed over by March 2017, eight (8) months after the completion period, but during physical verification, there was no evidence of work done at the site. The contractor abandoned the contract.

Contractor

N/A

Beneficial Ownership Information

N/A

Legislative Recommendation

N/A

Executive Action

N/A

Progress Report

N/A

Data Source

2017 Audit Report of the Federation

Project Gallery

Click to enlarge image

Seach for project by title, MDA, state, status, year…

Trending projects

Report project
in your community today

Do you know of project(s) in your community that has been abandoned, not executed or poorly implemented. Our team is ready to help you track it and get government to act.

Value for Money allows you to track, report and act on audited development projects abandoned, not executed or poorly implemented in your community to ensure public funds are efficiently, effectively, and economically utilized to improve service delivery to you and other citizens in Nigeria

Contact

Newsletter

Stay in the loop, get all project updates straight in your inbox. 

© 2024 Value for Money. All right reserved.