MDA

Ministry Of Foreign Affairs

Project Location/State

N/A State

Award Year

2018

Contract Sum

₦₦419,178,396.00

Amount Paid

₦₦419,178,396.00

Unaccounted

₦₦321,619,192.01

Context/Observation

Audit observed that the sum of N419,178,396.00 was allocated for “Linking Remote Site (Missions and Headquarters on the MPLS Optics Fibre) and Satellite Space Segment”, a supposed contract completed in the year 2015 as contained in some documents reviewed. This was obtained through the Authority to incur expenditure (AIE): No. MFA/HQ/CAP/141/2016 dated 18th August 2016. However, the sum of N321,619,192.01 representing 75% of the said amount was found to have been diverted to Recurrent/Overhead expenditures. While the sum of N97,559,203.99 only was expended for the linking remote site. Further audit investigation revealed that the Ministry did not have access to the site due to an outstanding debt of N227,638,142.67 that should have been paid from the allocation earmarked. This anomaly is because the Ministry failed to follow due process in the disbursement of government funds and proper supervision of government projects as stated in FR 3115 (Poor Management of Cash).

Contractor

N/A

Beneficial Ownership Information

N/A

Legislative Recommendation

The Permanent Secretary is required to provide evidence of proper approval for the virement,failing which he is to recover the sum of N321,619,192.01 and pay back to the Consolidated
Revenue Fund. Sanctions within Financial Regulation 3106 should apply

Executive Action

N/A

Progress Report

N/A

Data Source

2018 Audit Report

Project Gallery

Click to enlarge image

No submitted petition history found

Want to submit petition to Anti-Corruption Agency on this issue?

Let our “VfM AI” tool help you generate a unique petition and send it instantly to your preferred Anti-Corruption Agency for investigation!

Use "Submit Petition" button below to proceed

Seach for project by title, MDA, state, status, year…

Trending projects

Report project
in your community today

Do you know of project(s) in your community that has been abandoned, not executed or poorly implemented. Our team is ready to help you track it and get government to act.

Value for Money allows you to track, report and act on audited development projects abandoned, not executed or poorly implemented in your community to ensure public funds are efficiently, effectively, and economically utilized to improve service delivery to you and other citizens in Nigeria

Contact

Newsletter

Stay in the loop, get all project updates straight in your inbox. 

© 2025 Value for Money. All right reserved.