MDA

Niger Delta Basin Development Authority (NDBDA)

Project Location/State

Undisclosed State

Award Year

2012

Contract Sum

₦35.8m

Amount Paid

₦40.5m

Unaccounted

₦13.7m

Context/Observation

Contract was awarded to a company through a letter referenced AD/NDBDA/C/20/12/003 and dated 18th October, 2012 with a completion period of 6 ½ weeks.
rnExamination of payment vouchers revealed that the sum of N35,790,339.22 paid to the contractor included contingency provisions of N3,509,560.00. Neither the reason for the inclusion nor justification for utilization of the contingency sum was provided.

rnrn

During site inspection, it was observed that some provisions of the BEME were not carried out as stated. These provisions constituted job not done and the value, including the payment of contingency without detailed evidence of utilization, was put at N13,693,866.28.

Contractor

N/A

Beneficial Ownership Information

N/A

Legislative Recommendation

N/A

Executive Action

N/A

Progress Report

N/A

Data Source

2015 Audit report of F.G

Project Gallery

Click to enlarge image

Seach for project by title, MDA, state, status, year…

Trending projects

Report project
in your community today

Do you know of project(s) in your community that has been abandoned, not executed or poorly implemented. Our team is ready to help you track it and get government to act.

Value for Money allows you to track, report and act on audited development projects abandoned, not executed or poorly implemented in your community to ensure public funds are efficiently, effectively, and economically utilized to improve service delivery to you and other citizens in Nigeria

Contact

Newsletter

Stay in the loop, get all project updates straight in your inbox. 

© 2024 Value for Money. All right reserved.