MDA

Engineering Material Development Institute, Akure

Project Location/State

N/A State

Award Year

2018

Contract Sum

₦₦0.00

Amount Paid

₦₦29,451,649.28

Unaccounted

₦₦29,451,649.28

Context/Observation

Audit observed that nine (9) payment vouchers in the sum of N29,451,649.28 raised and paid between March and December, 2018 were not supported with necessary documents such as letter of Award, delivery note, and details of the cost contrary to the provision of the extant law above. Consequently, these payments cannot be regarded as legitimate charge against public funds.

Contractor

N/A

Beneficial Ownership Information

N/A

Legislative Recommendation

The Managing Director is required to account for the sum of N29,451,649.28 otherwise be sanction in accordance with the provision of FR 3106 should apply.

Executive Action

N/A

Progress Report

N/A

Data Source

2018 Audit Report of FG

Project Gallery

Click to enlarge image

No submitted petition history found

Want to submit petition to Anti-Corruption Agency on this issue?

Let our “VfM AI” tool help you generate a unique petition and send it instantly to your preferred Anti-Corruption Agency for investigation!

Use "Submit Petition" button below to proceed

Seach for project by title, MDA, state, status, year…

Trending projects

Report project
in your community today

Do you know of project(s) in your community that has been abandoned, not executed or poorly implemented. Our team is ready to help you track it and get government to act.

Value for Money allows you to track, report and act on audited development projects abandoned, not executed or poorly implemented in your community to ensure public funds are efficiently, effectively, and economically utilized to improve service delivery to you and other citizens in Nigeria

Contact

Newsletter

Stay in the loop, get all project updates straight in your inbox. 

© 2025 Value for Money. All right reserved.