MDA

Nigerian Ports Authority (NPA)

Project Location/State

Award Year

2019

Contract Sum

₦₦0.00

Amount Paid

₦₦0.00

Unaccounted

₦₦0.00

Context/Observation

1. Contract for the construction, delivery & commissioning of 100 Nos. of “R” Class MDPE Channel Marking Buoys, was awarded to a company on 2nd June, 2011 at a contract sum of US$5,781,615.00 (Five million, seven hundred and eighty-one thousand, six hundred and fifteen Dollars);
2.The contractor was later paid 15% advance payment as mobilization fee of US$867,242.25 (Eight hundred and sixty-seven thousand, two hundred and forty-two Dollars, twenty-five cents) which was supported with a Bank Advance Payment Guarantee (APG) dated 7th June 2011;
3. The contract was awarded in foreign currency denomination, in contravention of Financial Regulations 2914.
4. Despite the fact that a tenderer quoted the sum of US$3,574,216.80, being the lowest bid for the job, the Parastatal Tenders Board (PTB), however, recommended that the contract should be awarded to another tenderer who quoted US$5,781,615.00 (Five Million, seven hundred and eighty-one thousand, six hundred and fifteen Dollars), the third lowest bid, claiming that the contract may be abandoned if awarded to the tenderer with the lowest bid.
5.The preferred bidder refused to refund the advance payment of US$867,242.25 (Eight hundred and sixty-seven thousand, two hundred and forty-two Dollars, twenty-five cents) upon the termination the contract through a letter with Ref. No. HQ/GM/PROC/AD/T.4/478 dated 23rd April 2012, following a directive by the Bureau for Public Procurement, in response to a petition by the lowest bidder, and
6.The directive by the Authority to the contractor to keep the advance payment in an Escrow account until the issues are resolved was not complied with.

Contractor

N/A

Beneficial Ownership Information

N/A

Legislative Recommendation

Recommendations
The Managing Director is requested to:
i. Provide reasons for the award of contract in foreign denomination in flagrant violation of the provisions of FR 2914.
ii. Recover the 15% mobilization fee of US$867,242.25 (Eight hundred and sixty seven thousand, two hundred and forty-two Dollars, twenty-five cents) paid the initial contractor and remit same to the Treasury, and
iii. Forward evidence of remittance to the Public Accounts Committees of the National Assembly, and
Iv. Otherwise, apply sanction relating to irregular award of contract stated in paragraph 3117 of the Financial Regulations

Executive Action

N/A

Progress Report

N/A

Data Source

2019 Non compliance Audit report of the FG

Project Gallery

Click to enlarge image

No submitted petition history found

Want to submit petition to Anti-Corruption Agency on this issue?

Let our “VfM AI” tool help you generate a unique petition and send it instantly to your preferred Anti-Corruption Agency for investigation!

Use "Submit Petition" button below to proceed

Seach for project by title, MDA, state, status, year…

Trending projects

Report project
in your community today

Do you know of project(s) in your community that has been abandoned, not executed or poorly implemented. Our team is ready to help you track it and get government to act.

Value for Money allows you to track, report and act on audited development projects abandoned, not executed or poorly implemented in your community to ensure public funds are efficiently, effectively, and economically utilized to improve service delivery to you and other citizens in Nigeria

Contact

Newsletter

Stay in the loop, get all project updates straight in your inbox. 

© 2025 Value for Money. All right reserved.