MDA

Federal College of Education (Technical) Umunze, Anambra State

Project Location/State

Anambra State

Award Year

Contract Sum

₦514.2m

Amount Paid

₦77.1m

Unaccounted

₦56.2m

Context/Observation

Sections 35 (1) of Part VI of the Public Procurement Act, 2007 which provides that a mobilization fees of not more than 15% may be paid to a supplier or contractor supported by Advance Payment Guarantee (APG). Furthermore, Section 35 (2) states that once a mobilization fee has been paid to any supplier or contractor, no further payment shall be made to a contractor/supplier outside the 15% mobilization fee, except upon a certificate of performance, or a performance bond/guarantee.
Examination of 3 contracts revealed that the College amortized the recovery of mobilization fees totalling ₦77,135,922.50 by deducting only one-third (1/3) of the amount on Valuation Certificate No.1 instead of full recovery of the 15% advance payments from the sum due to the contractors. By amortizing the recovery of the mobilization fee, the College was craftily paying the contractors above what should have been paid to them on subsequent Valuation Certificates.

Contractor

JULLYMOO VENTURES LTD

Beneficial Ownership Information

N/A

Legislative Recommendation

N/A

Executive Action

N/A

Progress Report

N/A

Data Source

2017 Audit Report of the Federation

Project Gallery

Click to enlarge image

No submitted petition history found

Want to submit petition to Anti-Corruption Agency on this issue?

Let our “VfM AI” tool help you generate a unique petition and send it instantly to your preferred Anti-Corruption Agency for investigation!

Use "Submit Petition" button below to proceed

Seach for project by title, MDA, state, status, year…

Trending projects

Report project
in your community today

Do you know of project(s) in your community that has been abandoned, not executed or poorly implemented. Our team is ready to help you track it and get government to act.

Value for Money allows you to track, report and act on audited development projects abandoned, not executed or poorly implemented in your community to ensure public funds are efficiently, effectively, and economically utilized to improve service delivery to you and other citizens in Nigeria

Contact

Newsletter

Stay in the loop, get all project updates straight in your inbox. 

© 2024 Value for Money. All right reserved.